25 Group orders

This special function adjusts the time of started orders to be exactly the same, even if that isn't the case.
The function is intended to be used together with special functions 30, 31, and 33.

OBS: Please note that this special function will change the standard logic in Balthzar eTouch so that the following will always happen:

1) When the first report is done on a planned order, the working order is created with the start date "now", after this is done the report will be done and the order will be finished.

2) Reports following the first one will happen on the order created in step 1 and they will also delay the end date to the following orders "now".

The picture below shows a timeline which will illustrate the reasoning behind this workflow.  

A report is happening in step 1, one order is created.
A new report, the last one for the current order is created at step 2 and the order is finished.
The order is started again at a later date and time at step 3.
Another report is made at step 4 and the order is finished.

The order has now received the start time from step 1 and the end time from step 4 even though that is not the case in reality.

Reviewed statistics based on orders starttime and endtime need to keep this in mind.

This special function CAN NOT be used togheter with the function to scrap against previous operation.
If prima quantity is reported on the action when previous reported + scrapped quantity + now reported quantity is bigger then planned quantity a question will be delivered weather or not the order is fully reported. If the user answer "Yes" on this question a revoquation will automatically be created for that specific reportnumber.